D1.1 | Project Management Handbook Due Date (Month) – M3, Mart 2024 |
INM DIH | |||
D6.1 | Initial Communication and dissemination plan including Exploitation Strategy Due Date (Month) – M4, April 2024 |
AMB
|
|||
D6.4 |
Project image and website |
||||
D6.5 | Established social media channels Due Date (Month) – M4, April 2024 |
||||
D1.2 | Quality Plan (QP) Due Date (Month) – M5, May 2024 |
INM DIH | |||
D1.3 | Initial Risk Management Plan (RMP) Due Date (Month) – M5, May 2024 |
INM DIH | |||
D1.5 | Initial Data Management Plan (DMP) Date (Month) – M6, June 2024 |
AKI | |||
D2.1 | Initial guideline for network establishment, governance and management Date (Month) – M6, June 2024 |
BEC | |||
D2.5 | Map of OGs, networks and key actors engaged within the project Date (Month) – M6, June 2024 |
BOKU | |||
D2.7 | Initial Synergy Map of EU networks, smilar projects and initiative Date (Month) – M6, June 2024 |
BEC | |||
D2.3 | Initial report on National Nodes and Soil-X-Change establishment management Due Date (Month) – M9, September 2024 |
BEC | |||
D2.6 | 9 Letter of support signed by AKIS Coordination bodies from Member states Due Date (Month) – M9, September 2024 |
||||
D4.1 | A well-developed and documented database including survey results Due Date (Month) – M12, December 2024 |
DC | |||
D6.6 | Initial engagement metrics analysis report including actions for improvement Due Date (Month) – M12, December 2024 |
INM DIH | |||
D4.2 | Analysis report of the survey data Due Date (Month) – M4, April 2025 |
DC | |||
D2.2 | Updated guideline for network establishment, governance and management Date (Month) – M6, June 2025 |
BEC | |||
D2.4 | Updated report on National Nodes and Soil-X-Change establishment and management Date (Month) – M6, June 2025 |
BEC | |||
D2.9 | Outcome report of events organized with AKISs in the first half of the project Date (Month) – M6, June 2025 |
BEC | |||
D2.8 | Updates Synergy Map of EU networks, similar projects and initiative Date (Month) – M6, June 2025 |
BEC | |||
D4.3 | Data Dashboard presenting research findings in a visual and easy-to-undestand language Date (Month) – M6, June 2025 |
DC | |||
D6.2 | Updated Communication and dissemination plan including Exploitation Strategy Date (Month) – M6, June 2025 |
AMB | |||
D6.7 | Updated engagement metrics analysis report including actions for improvement Date (Month) – M6, June 2025 |
INM DIH | |||
D6.9 | 15 EIP AGRI practice abstracts - Batch 1 Date (Month) – M6, June 2025 |
DC | |||
D1.4 | Updated Risk Management Plan Due Date (Month) – M12, December 2025 |
INM DIH | |||
D1.6 | Updated Data Management Plan Due Date (Month) – M12, December 2025 |
AKI | |||
D5.1 | "How to build soil Living Lab including organization of farm demonstration" Guide Due Date (Month) – M12, December 2025 |
BEC | |||
D6.3 | 2. Updated Communication and dissemintaion plan including Exploitation Strategy Due Date (Month) – M12, December 2025 |
AMB | |||
D6.8 | 2. Updated engagement metrics analysis report including actions for improvement Due Date (Month) – M12, December 2025 |
INM DIH | |||
D4.4 | Report with the feedback of users on the data dashboard Due Date (Month) – M1, January 2026 |
DC | |||
D5.3 | Cost- benefit and impact analysis of the selected 18 use cases Due Date (Month) – M4, April 2026 |
AKI | |||
D3.1 | Updated Synergy Map of EU networks, similar projects and initiatives Date (Month) – M6, June 2026 |
BOKU | |||
D3.2 | Policy recommendations on Operational Group establishment, management and funding in EU countries Date (Month) – M8, August 2026 |
||||
D3.3 | National/Regional Policy recommendation on sustainable soil and farm management Date (Month) – M8, August 2026 |
DC | |||
D3.4 | Outcome report of events organized with AKISs in the second half of the project Date (Month) – M8, August 2026 |
||||
D5.2 | 18 farm demonstration video materials Date (Month) – M8, August 2026 |
AKI | |||
D4.5 | Adaptation guide of the selected 18 use cases to facilitate outscaling to other regions Date (Month) – M10, October 2026 |
ATB | |||
D6.10 | 45 EIP AGRI practice abstracts - Batch 2 Date (Month) – M10, October 2026 |
DC | |||
D6.11 | 2 scientific articles Date (Month) – M10, October 2026 |
ATB | |||
D6.12 | Sustainability strategy with roadmap Date (Month) – M10, October 2026 |
ATB | |||
D5.4 | Report on the national technical AKIS workshops organized in the second half of the project Due Date (Month) – M12, December 2026 |
AKI |