    D1.1 Project Management Handbook
Due Date (Month) – M3, Mart 2024
INM DIH
    D6.1 Initial Communication and dissemination plan including Exploitation Strategy 
Due Date (Month) – M4, April 2024

AMB

 

      D6.4

Project image and website
Due Date (Month) – M4, April 2024

      D6.5 Established social media channels
Due Date (Month) – M4, April 2024
    D1.2 Quality Plan (QP)
Due Date (Month) – M5, May 2024
INM DIH
      D1.3 Initial Risk Management Plan (RMP)
Due Date (Month) – M5, May 2024
INM DIH
    D1.5 Initial Data Management Plan (DMP)
Date (Month) – M6, June 2024
AKI
      D2.1 Initial  guideline for network establishment, governance and management
Date (Month) – M6, June 2024
BEC
      D2.5 Map of OGs, networks and key actors engaged within the project
Date (Month) – M6, June 2024
BOKU
      D2.7 Initial Synergy Map of EU networks, smilar projects and initiative
Date (Month) – M6, June 2024
BEC
    D2.3 Initial report on National Nodes and Soil-X-Change establishment management
Due Date (Month) – M9, September 2024
BEC
      D2.6 9 Letter of support signed by AKIS Coordination bodies from Member states
Due Date (Month) – M9, September 2024
    D4.1 A well-developed and documented database including survey results
Due Date (Month) – M12, December 2024
DC
      D6.6 Initial engagement metrics analysis report including actions for improvement
Due Date (Month) – M12, December 2024
INM DIH
    D4.2 Analysis report of the survey data
Due Date (Month) – M4, April 2025
DC
    D2.2 Updated guideline for network establishment, governance and management
Date (Month) – M6, June 2025
BEC
      D2.4 Updated report on National Nodes and Soil-X-Change establishment and management
Date (Month) – M6, June 2025
BEC
      D2.9 Outcome report of events organized with AKISs in the first half of the project
Date (Month) – M6, June 2025
BEC
      D2.8 Updates Synergy Map of EU networks, similar projects and initiative
Date (Month) – M6, June 2025
BEC
      D4.3 Data Dashboard presenting research findings in a visual and easy-to-undestand language
Date (Month) – M6, June 2025
DC
      D6.2 Updated Communication and dissemination plan including Exploitation Strategy
Date (Month) – M6, June 2025
AMB
      D6.7 Updated engagement metrics analysis report including actions for improvement
Date (Month) – M6, June 2025
INM DIH
      D6.9 15 EIP AGRI practice abstracts - Batch 1
Date (Month) – M6, June 2025
DC
    D1.4 Updated Risk Management Plan
Due Date (Month) – M12, December 2025
INM DIH
      D1.6 Updated Data Management Plan
Due Date (Month) – M12, December 2025
AKI
      D5.1 "How to build soil Living Lab including organization of farm demonstration" Guide
Due Date (Month) – M12, December 2025
BEC
      D6.3 2. Updated Communication and dissemintaion plan including Exploitation Strategy
Due Date (Month) – M12, December 2025
AMB
      D6.8 2. Updated engagement metrics analysis report including actions for improvement
Due Date (Month) – M12, December 2025
INM DIH
    D4.4 Report with the feedback of users on the data dashboard
Due Date (Month) – M1, January 2026
DC
    D5.3 Cost- benefit and impact analysis of the selected 18 use cases
Due Date (Month) – M4, April 2026
AKI
    D3.1 Updated Synergy Map of EU networks, similar projects and initiatives
Date (Month) – M6, June 2026
BOKU
    D3.2 Policy recommendations on Operational Group establishment, management and funding in EU countries
Date (Month) – M8, August 2026
      D3.3 National/Regional Policy recommendation on sustainable soil and farm management
Date (Month) – M8, August 2026
DC
      D3.4 Outcome report of events organized with AKISs in the second half of the project
Date (Month) – M8, August 2026
      D5.2 18 farm demonstration video materials
Date (Month) – M8, August 2026
AKI
    D4.5 Adaptation guide of the selected 18 use cases to facilitate outscaling to other regions
Date (Month) – M10, October 2026
ATB
      D6.10 45 EIP AGRI practice abstracts - Batch 2
Date (Month) – M10, October 2026
DC
      D6.11 2 scientific articles
Date (Month) – M10, October 2026
ATB
      D6.12 Sustainability strategy with roadmap
Date (Month) – M10, October 2026
ATB
    D5.4 Report on the national technical AKIS workshops organized in the second half of the project
Due Date (Month) – M12, December 2026
AKI